Bridges

Bridge (Intersection of Abu Baker Siddiq Rd. & King Abdullah Rd.) – Tabuk

48.6M

SAR

Total value

2017

-

Completion date

Project duration: 24 months
Bridge rump 300m include 2 Direction with 2 traffic lanes in each direction
Volume of concrete: 3,500 m3
Excavation: 35,000 m3
Steel: 4,000 tons

Bridges

Box Culvert (Masara with Jesh) – Taif

Next Project