Bridges

Bridge (Intersection of Abu Baker Al-Siddiq Rd. & King Abdullah Rd.) – Tabuk

48.6M

SAR

Total value

2017

-

Completion date

Project duration: 24 months
Bridge rump 300m include 2 Direction with 2 traffic lanes in each direction
Volume of concrete: 3,500 m³
Excavation: 35,000 m³
Steel: 4,000 t